Agile Testing appears throughout Manual Testing interviews. At medium level, interviewers are typically checking that you have used it in practice: what you configured, what broke, and how you knew it worked. Work through these, then explain your answer out loud; the second part is what interviews actually test.
20 example questions
1. "Criteria a story must meet before entering a sprint" — in Agile, this describes which of the following?
- A. Sprint backlog.
- B. Three amigos.
- C. DoR (Definition of Ready).correct
- D. User story.
Why: DoR (Definition of Ready): Criteria a story must meet before entering a sprint.
2. Which of the following statements about Agile is TRUE?
- A. Test charters and session-based test management structure exploratory work in sprints.correct
- B. Acceptance criteria are written only after the story is released.
- C. Agile testing occurs only after all sprints are complete.
- D. Testers must never speak during refinement or planning.
Why: Timeboxed sessions make exploratory testing plannable and reportable.
3. "Work the team commits to for the sprint" — in Agile, this describes which of the following?
- A. Sprint backlog.correct
- B. Velocity.
- C. INVEST.
- D. DoR (Definition of Ready).
Why: sprint backlog: Work the team commits to for the sprint.
4. Identify the accurate statement about Agile:
- A. A sprint review demonstrates the increment; a retrospective improves the process.correct
- B. A retrospective is a demo of the product for stakeholders.
- C. The Definition of Done forbids including testing activities.
- D. Automation should always be deferred several sprints behind development.
Why: Review inspects the product; retro inspects the way of working.
5. "Small unit of value from a user perspective" — in Agile, this describes which of the following?
- A. DoR (Definition of Ready).
- B. Increment.
- C. Sprint backlog.
- D. User story.correct
Why: user story: Small unit of value from a user perspective.
6. "Potentially shippable product output of a sprint" — in Agile, this describes which of the following?
- A. Increment.correct
- B. INVEST.
- C. DoR (Definition of Ready).
- D. Burndown chart.
Why: increment: Potentially shippable product output of a sprint.
7. "Quality checklist for good user stories" — in Agile, this describes which of the following?
- A. Sprint backlog.
- B. INVEST.correct
- C. User story.
- D. Three amigos.
Why: INVEST: Quality checklist for good user stories.
8. Which statement correctly describes Agile?
- A. Agile testing occurs only after all sprints are complete.
- B. Acceptance criteria are written only after the story is released.
- C. Test charters and session-based test management structure exploratory work in sprints.correct
- D. Automation should always be deferred several sprints behind development.
Why: Timeboxed sessions make exploratory testing plannable and reportable.
9. In Agile, which of the following is described as: "Business, developer, tester collaboration on examples"?
- A. Burndown chart.
- B. Sprint backlog.
- C. Three amigos.correct
- D. User story.
Why: three amigos: Business, developer, tester collaboration on examples.
10. In the context of Agile, which of the following is a correct statement?
- A. A retrospective is a demo of the product for stakeholders.
- B. Acceptance criteria are written only after the story is released.
- C. Automation should always be deferred several sprints behind development.
- D. Test charters and session-based test management structure exploratory work in sprints.correct
Why: Timeboxed sessions make exploratory testing plannable and reportable.
11. Which Agile concept matches this description: "Business, developer, tester collaboration on examples"?
- A. Sprint backlog.
- B. User story.
- C. Three amigos.correct
- D. DoR (Definition of Ready).
Why: three amigos: Business, developer, tester collaboration on examples.
12. In Agile, which of the following is described as: "Criteria a story must meet before entering a sprint"?
- A. INVEST.
- B. User story.
- C. Velocity.
- D. DoR (Definition of Ready).correct
Why: DoR (Definition of Ready): Criteria a story must meet before entering a sprint.
13. In Agile, which of the following is described as: "Work the team commits to for the sprint"?
- A. Three amigos.
- B. Sprint backlog.correct
- C. Increment.
- D. INVEST.
Why: sprint backlog: Work the team commits to for the sprint.
14. Which Agile concept matches this description: "Visualization of remaining work in a sprint"?
- A. INVEST.
- B. Burndown chart.correct
- C. Velocity.
- D. DoR (Definition of Ready).
Why: burndown chart: Visualization of remaining work in a sprint.
15. In Agile, which of the following is described as: "Quality checklist for good user stories"?
- A. User story.
- B. Increment.
- C. INVEST.correct
- D. DoR (Definition of Ready).
Why: INVEST: Quality checklist for good user stories.
16. Which Agile concept matches this description: "Quality checklist for good user stories"?
- A. Sprint backlog.
- B. Three amigos.
- C. INVEST.correct
- D. User story.
Why: INVEST: Quality checklist for good user stories.
17. Which Agile concept matches this description: "Measure of completed story points per sprint"?
- A. DoR (Definition of Ready).
- B. INVEST.
- C. Velocity.correct
- D. Increment.
Why: velocity: Measure of completed story points per sprint.
18. Which Agile concept matches this description: "Work the team commits to for the sprint"?
- A. Burndown chart.
- B. DoR (Definition of Ready).
- C. Sprint backlog.correct
- D. Increment.
Why: sprint backlog: Work the team commits to for the sprint.
19. Regarding Agile, which statement is correct?
- A. Continuous testing runs automated checks throughout the delivery pipeline.correct
- B. Automation should always be deferred several sprints behind development.
- C. A retrospective is a demo of the product for stakeholders.
- D. Agile testing occurs only after all sprints are complete.
Why: Quality feedback accompanies every change, not just releases.
20. Which Agile concept matches this description: "Potentially shippable product output of a sprint"?
- A. Burndown chart.
- B. INVEST.
- C. Velocity.
- D. Increment.correct
Why: increment: Potentially shippable product output of a sprint.